May 2019 – Construction Update

This update provides a snapshot of current and upcoming works for the month of May.


RECENT MILESTONES
Bcentral would like to report that construction is progressing at a steady pace.

The Heart building has advanced with the installation of the roof plumbing, roof sheeting and windows.

The services rough in is 90% complete to the apartments.

The internal studwork has been completed to the apartments with the plaster currently being flushed and sanded.

The Sky building saw the remaining concrete slab being poured prior to the Easter break.

The concreters have tensioned all the slabs and have commenced stripping formwork up to Level 1.

The structural steelwork is underway and is commencing to Level 5. This also includes steelwork to the Ground Floor canopy.

 

UPCOMING WORKS
The services rough in and other works are to be completed towards the end of May on the Heart building with kitchen installations having commenced.

The façade will begin to take shape and colour with external cladding works to be installed and render to be applied.

Balconies will be waterproofed and screeded with apartment bathrooms also to be prepared for tiling.

The Sky building will see the formwork all stripped by the end of the month to allow services rough in to commence to the lower levels. Structural steelwork, roof plumbing and roof sheeting will be completed towards the end of May.

 

OVERALL PROGRAM
Completion is currently expected in the fourth quarter of 2019 with settlements to follow thereafter.