August 2019 – Construction Update

This update provides a snapshot of current and upcoming works for the month of August/September.

RECENT MILESTONES

BCENTRAL would like to report that great progress has been made at both the Sky and Heart buildings over the last month. The internal fitout of the apartments is taking shape and colour with the installation of the joinery, stone benchtops, splashbacks, mirrors and tiling.

Sky building

  • The gantry has been removed to the pedestrian footpath now revealing the retail shopfronts
  • Plastering of ceilings to the lower levels has been completed
  • Kitchen joinery has been installed from Level 1 to Level 3
  • Bathrooms and external balconies have been waterproofed and screeded with tiling having commenced to the lower levels
  • The installation of splashbacks and mirrors has commenced
  • Robe installation is underway to the lower levels

 

Heart building

  • Kitchen and bathroom joinery has been installed
  • Bathroom tiling works has been completed
  • Robes have been installed
  • Stone benchtops, splashbacks and mirrors have been installed
  • Timber flooring installation has commenced
  • Painting works have commenced

 

UPCOMING WORKS

Sky building

  • The crane will be removed early September.
  • Plastering of ceilings to be completed to the upper levels
  • Tiling works to commence to the upper levels
  • Balcony pavers to be installed to the lower levels
  • Kitchen joinery and robes will be installed to the upper levels
  • Timber flooring shortly to commence

 

Heart building

  • Services fit off to be completed
  • Painting works to be completed internally to apartments
  • Appliances to be installed
  • Carpet works to commence
  • Foyer fitout to commence

 

OVERALL PROGRAM

Completion is currently expected in the fourth quarter of 2019 with settlements to follow thereafter.