This update provides a snapshot of current and upcoming works for the month of May.
RECENT MILESTONES
Bcentral would like to report that construction is progressing that great progress has been made at both the Sky and Heart buildings over the last month. The building is taking shape and colour with the installation of the external cladding and render applied.
Sky building:
• The structural steelwork to Level 5 and Ground Floor canopy was completed.
• 80% of the aluminium windows have been installed
• The services rough-ins were completed to the lower levels
• Bathrooms and external balconies are being waterproofed and screeded in preparation for tiling.
Heart building:
• Kitchen and bathroom joinery installation has commenced
• Bathroom tiling works has commenced
• Robe installation is underway
• Services fit off is underway to Level 3
• Splashbacks and mirrors have been measured
UPCOMING WORKS
Sky building:
• The services rough-in and plaster walls through to Level 5 is to be completed
• Plastering of the ceilings is to commence
• Tiling will commence to lower Levels 1 to 3
• Kitchen joinery is to commence
Heart building:
• Completion of the installation of kitchen and bathroom joinery
• Services fit off to all apartments
• Installation of stone benchtops
• Installation of splashbacks and mirrors
OVERALL PROGRAM
Completion is current expected in the fourth quarter of 2019 with settlements to follow thereafter.