Construction Updates

Nov/Dec 2019 – Construction UpdateNov/Dec 2019 – Construction Update
Nov/Dec 2019 – Construction Update

This update provides a snapshot of current and upcoming works for the month of November/December.

RECENT MILESTONES

BCENTRAL would like to report that the finishing trades have almost been completed to both the Sky and Heart buildings as we move closer towards completion.

Sky building

  • Glazing components have been completed
  • Painting currently being completed

Heart building

  • Timber flooring and carpet have been installed
  • Painting touch ups and completion of finishing trades

 

UPCOMING WORKS

Sky building

  • Completion of timber and carpet
  • Appliances to be installed
  • Completion of Foyer works
  • Services testing and commissioning

Heart building

  • Completion of Foyer works
  • Services testing and commissioning

Common areas

  • Service meter cupboards have been installed
  • Civil external works including footpaths and crossovers have been completed
  • Epoxy works to the basement are being completed with linemarking to follow
  • Basement storage cages are being installed
  • Signage to be installed

 

OVERALL PROGRAM

Completion is currently expected in the fourth quarter of 2019 with settlements to follow thereafter.

October 2019 – Construction UpdateOctober 2019 – Construction Update
October 2019 – Construction Update

This update provides a snapshot of current and upcoming works for the month of October.

RECENT MILESTONES

BCENTRAL would like to report that the finishing trades have advanced to both the Sky and Heart buildings over the last month as we move closer towards completion.

Sky building

  • The crane was removed in September
  • The retail shopfronts are now revealed and canopies completed
  • Plastering of walls and ceilings have been completed
  • Splash backs, shower screens and mirrors have been completed up to
    Level 3
  • The kitchen joinery and robes have been installed
  • Tiling has been completed to wet areas and balconies

Heart building

  • The lift has been installed and being commissioned
  • Timber flooring to be completed
  • Appliances have been installed
  • Painting has been completed internally to apartments

 

UPCOMING WORKS

Sky building

  • Timber flooring to be installed
  • Carpet to be installed
  • Appliances to be installed
  • The lift is to be installed and commissioned
  • Foyer fit-out to commence

Heart building

  • Carpet to be installed
  • Foyer fitout to commence
  • Painting to common areas to be completed

Common areas

  • Civil external works including footpaths and crossovers to commence
  • Epoxy works to basement to be done
  • Basement storage cages to be installed and linemarking to commence
  • Service meter cupboards to be installed

 

OVERALL PROGRAM

Completion is currently expected in the fourth quarter of 2019 with settlements to follow thereafter.

August 2019 – Construction UpdateAugust 2019 – Construction Update
August 2019 – Construction Update

This update provides a snapshot of current and upcoming works for the month of August/September.

RECENT MILESTONES

BCENTRAL would like to report that great progress has been made at both the Sky and Heart buildings over the last month. The internal fitout of the apartments is taking shape and colour with the installation of the joinery, stone benchtops, splashbacks, mirrors and tiling.

Sky building

  • The gantry has been removed to the pedestrian footpath now revealing the retail shopfronts
  • Plastering of ceilings to the lower levels has been completed
  • Kitchen joinery has been installed from Level 1 to Level 3
  • Bathrooms and external balconies have been waterproofed and screeded with tiling having commenced to the lower levels
  • The installation of splashbacks and mirrors has commenced
  • Robe installation is underway to the lower levels

 

Heart building

  • Kitchen and bathroom joinery has been installed
  • Bathroom tiling works has been completed
  • Robes have been installed
  • Stone benchtops, splashbacks and mirrors have been installed
  • Timber flooring installation has commenced
  • Painting works have commenced

 

UPCOMING WORKS

Sky building

  • The crane will be removed early September.
  • Plastering of ceilings to be completed to the upper levels
  • Tiling works to commence to the upper levels
  • Balcony pavers to be installed to the lower levels
  • Kitchen joinery and robes will be installed to the upper levels
  • Timber flooring shortly to commence

 

Heart building

  • Services fit off to be completed
  • Painting works to be completed internally to apartments
  • Appliances to be installed
  • Carpet works to commence
  • Foyer fitout to commence

 

OVERALL PROGRAM

Completion is currently expected in the fourth quarter of 2019 with settlements to follow thereafter.

July 2019 - Construction UpdateJuly 2019 - Construction Update
July 2019 - Construction Update

This update provides a snapshot of current and upcoming works for the month of May.


RECENT MILESTONES
Bcentral would like to report that construction is progressing that great progress has been made at both the Sky and Heart buildings over the last month. The building is taking shape and colour with the installation of the external cladding and render applied.

 

Sky building:
• The structural steelwork to Level 5 and Ground Floor canopy was completed.
• 80% of the aluminium windows have been installed
• The services rough-ins were completed to the lower levels
• Bathrooms and external balconies are being waterproofed and screeded in preparation for tiling.

 

Heart building:
• Kitchen and bathroom joinery installation has commenced
• Bathroom tiling works has commenced
• Robe installation is underway
• Services fit off is underway to Level 3
• Splashbacks and mirrors have been measured

UPCOMING WORKS

Sky building:
• The services rough-in and plaster walls through to Level 5 is to be completed
• Plastering of the ceilings is to commence
• Tiling will commence to lower Levels 1 to 3
• Kitchen joinery is to commence

Heart building:
• Completion of the installation of kitchen and bathroom joinery
• Services fit off to all apartments
• Installation of stone benchtops
• Installation of splashbacks and mirrors

OVERALL PROGRAM

Completion is current expected in the fourth quarter of 2019 with settlements to follow thereafter.

May 2019 - Construction UpdateMay 2019 - Construction Update
May 2019 - Construction Update

This update provides a snapshot of current and upcoming works for the month of May.


RECENT MILESTONES
Bcentral would like to report that construction is progressing at a steady pace.

The Heart building has advanced with the installation of the roof plumbing, roof sheeting and windows.

The services rough in is 90% complete to the apartments.

The internal studwork has been completed to the apartments with the plaster currently being flushed and sanded.

The Sky building saw the remaining concrete slab being poured prior to the Easter break.

The concreters have tensioned all the slabs and have commenced stripping formwork up to Level 1.

The structural steelwork is underway and is commencing to Level 5. This also includes steelwork to the Ground Floor canopy.

 

UPCOMING WORKS
The services rough in and other works are to be completed towards the end of May on the Heart building with kitchen installations having commenced.

The façade will begin to take shape and colour with external cladding works to be installed and render to be applied.

Balconies will be waterproofed and screeded with apartment bathrooms also to be prepared for tiling.

The Sky building will see the formwork all stripped by the end of the month to allow services rough in to commence to the lower levels. Structural steelwork, roof plumbing and roof sheeting will be completed towards the end of May.

 

OVERALL PROGRAM
Completion is currently expected in the fourth quarter of 2019 with settlements to follow thereafter.

March 2019 - Construction UpdateMarch 2019 - Construction Update
March 2019 - Construction Update

Construction is continuing in Bentleigh at the site of the CIEL apartments.

This update provides a snapshot of current and upcoming works for the month of March.

RECENT MILESTONES

Construction is progressing well in Bentleigh at the site of the CIEL apartments.

There is plenty of excitement and buzz as the CIEL shadecloth was erected around the building site.

The months of February and March have seen the site become a hub of activity with the building rising out of the ground with the Sky building (Centre Rd) and Heart building (Browns Rd) beginning to take shape.

The structural works to the basement, ground and first floors have been completed.

The second floor has been poured to Level 2 with precast panels erected to Level 3 on the Sky building whilst the Heart building has been topped out with the third floor being poured and precast panels erected to this level.

 

UPCOMING WORKS
The concrete pours and precast panel erection will continue to the Sky building.

The framing and roughing out of services will commence on the Heart building next month.

 

More UPDATES TO COME +