Nov/Dec 2019 – Construction Update

This update provides a snapshot of current and upcoming works for the month of November/December.

RECENT MILESTONES

BCENTRAL would like to report that the finishing trades have almost been completed to both the Sky and Heart buildings as we move closer towards completion.

Sky building

  • Glazing components have been completed
  • Painting currently being completed

Heart building

  • Timber flooring and carpet have been installed
  • Painting touch ups and completion of finishing trades

 

UPCOMING WORKS

Sky building

  • Completion of timber and carpet
  • Appliances to be installed
  • Completion of Foyer works
  • Services testing and commissioning

Heart building

  • Completion of Foyer works
  • Services testing and commissioning

Common areas

  • Service meter cupboards have been installed
  • Civil external works including footpaths and crossovers have been completed
  • Epoxy works to the basement are being completed with linemarking to follow
  • Basement storage cages are being installed
  • Signage to be installed

 

OVERALL PROGRAM

Completion is currently expected in the fourth quarter of 2019 with settlements to follow thereafter.